TIIMS is a comprehensive information management system developed to support
environmental restoration and planning activities in the Lake TahoeBasin. Much
work has been done to ensure that TIIMS is a valuable resource for Basin stakeholders.
An extensive Requirements Analysis was conducted at the onset of the project
to identify information resources, information needs, information management
systems, and the desired functionality of TIIMS. In January 2004, the TIIMS
prototype, which incorporates the highest priority functions, was released.
One of the most important benefits of TIIMS is how it facilitates collaboration
and coordination of the many federal, state, and local agencies involved in
restoration efforts in the Basin. This makes TIIMS a valuable tool for agencies
that use the system. But, the continued development and success of TIIMS depends
on the continued support and participation of the Partner Agencies. For TIIMS
to move forward in a timely and efficient manner into the production phase (i.e.,
full development), several key steps need to happen. These steps relate to
(1) management needs, (2) systems support and development, and (3) development
of system standards and protocols. A commitment of both financial resources
and management and personnel support from participating agencies is needed to
ensure that these steps happen. A description of these steps and the estimated
costs are provided below. For ease of calculation, it is assumed that each
hour of labor, fully loaded, would cost approximately $100, and that there are
2,080 working hours in a year; costs are rounded up to the nearest $1,000.
Therefore, the estimated costs below are an approximation.
1.0 Management Needs
Developing a TIIMS administrative framework is critical to the future success
of TIIMS. The existing Project Team provides a good foundation for this structure
and has been integral to the development of the prototype. However, as the
system moves into full production, the time required to participate and oversee
the development of the system will increase. It is anticipated that the following
commitment of agency personnel will be needed in the next year to keep TIIMS
moving forward in a timely manner.
- A full-time TIIMS Coordinator. Once TIIMS moves into full production, it
will require a single person committed full time to oversee its development
and implementation. This is critical to the success of TIIMS. The TIIMS
Coordinator will be responsible for maintaining the momentum of the system
by developing MOUs; actively engaging in public outreach activities; and working
closely with the Project Team, Work Groups, and technical staff to coordinate
efforts and develop a long-term staff support and resource plan. ($208K)
- Project Team members will need to commit 16 hours per month to regularly
meet, review progress, and develop next steps. ($288K)
- Work Group members will need to commit a minimum of 24 hours per month to
address routine issues assigned to their group. Additional tasks will require
additional time for each Work Group member. ($288K)
2.0 System Support and Development
The prototype incorporates many high priority functions including the ability
to search, discover, and access metadata and data, as well as interactive mapping
capabilities including the ability to access real-time and historical data.
The following specific tasks conducted in the near future will help TIIMS move
into the Production Phase.
- Information Needs Coordinator. Continued evaluation of TIIMS information
needs against available information resources to develop a content acquisition
strategy and continue population of the metadata repository. This person
would work closely with the TIIMS Coordinator. Resources: one full-time
staff for 1.5 years ($312K). Each agency that is providing metadata and information
content to TIIMS would also need to dedicate 12 hours per month to this effort
($89K).
- Conduct public outreach activities. Though the TIIMS Coordinator will be
tasked with conducting public outreach activities, they cannot do this alone.
This is an essential element needed to garner support and users for TIIMS.
Public outreach workshops need to be conducted, and outreach materials, including
brochures and fact sheets, need to be developed. Resources: $150K (some of
which will be used for contractor support).
- Revise prototype based on user comments and integrate search engines. Contractor
support is needed for these two separate, but related, tasks. Resources:
1 to 2 full time equivalents (FTEs) for 10 months ($260K assuming 1.5 FTEs).
- Enhance workspace portal to provide more functions for document sharing
and revision. Additionally, conduct training seminars to review functionality
and encourage its use. Contractor support is expected to be needed for this
task ($100K).
- Develop and post electronic materials. This task is of the highest priority.
Resources: One full-time staff for 2 weeks, then 2 hours per week for the
next year ($18K)
- Edit all content contained on the TIIMS prototype for consistency in language
and format. Develop editorial standards for future content. Resources: One
full-time editor for 3 months ($52K).
- Provide technical support to Partner Agencies to help them establish a node
on the TIIMS network within the next year. Resources: one technical staff
person 6 months at half time ($52K). Hardware and software may need to be
purchased depending on the agency’s current system; costs could run up to
$20K.
3.0 Development of System Standards and Protocols
To ensure that high quality data and information are posted on TIIMS, data
standards and protocols need to be developed and implemented. Development of
these standards will be overseen by the relevant Work Group, with support from
technical staff as needed. Currently, three distinct tasks are the highest
priority:
- Develop monitoring protocols and data standards. This task will require
first assembling and reviewing existing standards, then conducting research
to develop new standards. The Work Group and Project Team members will need
to reach a consensus to implement the protocols and standards. Resources:
one full-time technical staff member for 6 months ($104K). Relevant Work
Group members will need to commit approximately 8 additional hours per month
to help develop the standards ($96K).
- Develop geographic reporting standards. This task will use the same approach
used to develop monitoring protocols and data standards. Resources: one full-time
technical staff for 1 month ($18K) and about 20 hours total for each relevant
Work Group member ($20K; $2K for each Work Group member).
- Develop and post TIIMS guidance manual. This documentation has been partially
developed for the prototype in terms of using TIIMS. Under this task, the
preliminary documentation will be augmented to include information on using
and supporting TIIMS, and how to become a Partner node. Resources: one person
full-time for 2 months ($35K).
| |
| Management Needs for First Year |
Costs (thousands of dollars) |
Percent of Total |
| |
TIIMS Coordinator |
$208 |
|
| |
Project Team Involvement (assumes 15 members)
|
$288 |
|
| |
Work Group (assumes 10 active members) |
$288 |
|
| |
Total Management Costs |
$784 |
37% |
| System Support & Development |
|
|
| |
Information Needs - Coordinator (1.5 years) |
$312 |
|
| |
Information Needs - Agency Contribution
(assumes 6 agencies) |
$89 |
|
| |
Conduct Public Outreach |
$150 |
|
| |
Revise Protoype & Integrate Search Engines |
$260 |
|
| |
Enhance Workspace Portal |
$100 |
|
| |
Develop & Post Electronic Materials |
$18 |
|
| |
Edit Prototype Content |
$52 |
|
| |
Technical Support to Develop Nodes |
$72 |
|
| |
Total System Support and Development
Costs |
$1,053 |
50% |
| Development of System Standards
and Protocols |
|
|
| |
Monitoring Protocols & Standards - Coordinator |
$104 |
|
| |
Monitoring Protocols & Standards - Work
Group Participation (assumes 10 active Work Group Members) |
$96 |
|
| |
Geographic Reporting Standards - Coordinator |
$18 |
|
| |
Geographic Reporting Standards - Work Group
Participation (assumes 10 active members) |
$20 |
|
| |
Develop & Post TIIMS Guidance Manual |
$35 |
|
| |
Total Development of System Standards
and Protocol Costs |
$273 |
13% |
| Total Costs to Move Into Production
Phase |
$2,110 |
100% |
| |
|
|
|
| |
|
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |